Obligated$315.00MCommitted by the government. Not cash paid.
OutlaysCash paid out so far.
Ceiling$315.00MBase plus all options. A maximum, not a payment.
Period of performanceSep 11, 2026 – Sep 30, 2030
Obligation timeline
Actions and modifications
Sep 11, 2026THE PURPOSE OF THIS DESIGN BUILD TO BUDGET AWARD IS FOR THE DESIGN AND CONSTRUCTION OF A FUEL PIER AND MAJOR CUTTER MOORING AT USCG BASE KODIAK, AK.$315.00MMod 0 · cumulative $315.00M
Oct 14, 2026THE PURPOSE OF THIS MODIFICATION IS TO UPDATE THE CONTRACTING OFFICERS REPRESENTATIVE. ALL OTHER ITEMS REMAIN UNCHANGED.$0Mod P00001 · cumulative $315.00M
Oct 26, 2026THE PURPOSE OF THIS MODIFICATION IS TO UPDATE THE CONTRACTING OFFICER'S REPRESENTATIVE (COR). THIS IS A NO COST TASK ORDER CHANGE. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.$0Mod P00002 · cumulative $315.00M
Record
Award ID
70Z05026F43000039
Category
contract
Industry (NAICS)
236220 · Commercial and Institutional Building Construction